Cash Flow Tip 9 - The Project Schedule and Cash Flow

The smoother the project schedule is, the smoother your cash flow will be.

D. Brown Management Profile Picture
Share

Large variations in the resource loading across a project’s duration impact cash flow and field productivity.  

Cash Flow: Tip 9 The Project Schedule and Cash Flow

Labor intensive contractors are impacted the worst because there is zero cash flow float on labor costs. Labor is paid within days of being incurred without any ability to stretch the payments out at all.  

The best schedule you can have for cash flow is one that ramps up smoothly, holds at peak production for a period of time, and then ramps down smoothly. The closer you can get to this schedule flow on your projects, the smoother they will run.

Schedule management starts with making clear production assumptions during the bid process and where applicable, getting those integrated into your contract.  

From there, focus on planning your project and keeping a level schedule flow in mind.  

Plan your Schedule-of-Values (SOV) for maximum cash flow based on the project schedule. 

Leverage your relationships to negotiate the best schedule flow and SOV you can.  

We are revamping our publicly available cash flow workshop that includes these 18 tactics that contractors can use to accelerate cash flow. Stay informed of updates on release.


Cash Flow Tip 9 - The Project Schedule and Cash Flow
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Cash Flow Tip 9 - The Project Schedule and Cash Flow
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Bill Walsh - Planning the First 25 Plays
Construction success depends on both the ability to rigorously plan as well as the ability to quickly react to changing field conditions. This is similar to sports and a lot can be learned from the disciplines of great coaches.
Growth or Attracting Talent
It’s not enough to just build work effectively - that is just what’s required to play in the game. Contractors seeking sustainable growth must have aggressive and balanced strategies for acquiring work and building talent.
Change Order Profit Improvement
A 10% improvement in change order pricing for a $50M per year contractor will add $500K to their bottom line. This is not about simply marking up the change more, but rather, including the many costs that are typically missed or undervalued.