Cash Flow Tip 9 - The Project Schedule and Cash Flow

The smoother the project schedule is, the smoother your cash flow will be.

D. Brown Management Profile Picture
Share

Large variations in the resource loading across a project’s duration impact cash flow and field productivity.  

Cash Flow: Tip 9 The Project Schedule and Cash Flow

Labor intensive contractors are impacted the worst because there is zero cash flow float on labor costs. Labor is paid within days of being incurred without any ability to stretch the payments out at all.  

The best schedule you can have for cash flow is one that ramps up smoothly, holds at peak production for a period of time, and then ramps down smoothly. The closer you can get to this schedule flow on your projects, the smoother they will run.

Schedule management starts with making clear production assumptions during the bid process and where applicable, getting those integrated into your contract.  

From there, focus on planning your project and keeping a level schedule flow in mind.  

Plan your Schedule-of-Values (SOV) for maximum cash flow based on the project schedule. 

Leverage your relationships to negotiate the best schedule flow and SOV you can.  

We are revamping our publicly available cash flow workshop that includes these 18 tactics that contractors can use to accelerate cash flow. Stay informed of updates on release.


Cash Flow Tip 9 - The Project Schedule and Cash Flow
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Cash Flow Tip 9 - The Project Schedule and Cash Flow
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Increased Value by Lowering Variability
A construction business is capable of providing a very high return to the owners who have their capital at risk as well as the team members that work there. Contractors with lower variability in profitability are both more valuable and more sustainable.
4 Different Strategic Planning Objectives
Before moving into a strategy or planning session, understand which of the four broad objectives you are working to accomplish knowing they may be different for different parts of the company.
Evolving Focus with Growth and Leadership Levels
All contractors are built on the same foundation, which starts with the amazing crafts people. With growth in the business, project size, and your level of leadership, the time you allocate to different layers of the pyramid must evolve.