Cash Flow Tip 9 - The Project Schedule and Cash Flow

The smoother the project schedule is, the smoother your cash flow will be.

D. Brown Management Profile Picture
Share

Large variations in the resource loading across a project’s duration impact cash flow and field productivity.  

Cash Flow: Tip 9 The Project Schedule and Cash Flow

Labor intensive contractors are impacted the worst because there is zero cash flow float on labor costs. Labor is paid within days of being incurred without any ability to stretch the payments out at all.  

The best schedule you can have for cash flow is one that ramps up smoothly, holds at peak production for a period of time, and then ramps down smoothly. The closer you can get to this schedule flow on your projects, the smoother they will run.

Schedule management starts with making clear production assumptions during the bid process and where applicable, getting those integrated into your contract.  

From there, focus on planning your project and keeping a level schedule flow in mind.  

Plan your Schedule-of-Values (SOV) for maximum cash flow based on the project schedule. 

Leverage your relationships to negotiate the best schedule flow and SOV you can.  

We are revamping our publicly available cash flow workshop that includes these 18 tactics that contractors can use to accelerate cash flow. Stay informed of updates on release.


Cash Flow Tip 9 - The Project Schedule and Cash Flow
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Cash Flow Tip 9 - The Project Schedule and Cash Flow
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Lean Principle - Value Add vs. Non Value Add
For specialty contractors the field workforce represents most of their competitive advantage as well as their biggest source of variability. Making improvements to field productivity requires deeply understanding what truly adds value to the customer.
Construction Labor Budget - Alternate Perspective
Improving craft labor productivity in construction will significantly reduce risk while providing a long-term competitive advantage for the contractor and every team member. This alternate labor budget perspective shows different opportunities.
Changes and Cash Flow Improvement
Construction is a cash-intensive business and change orders are often one of the root causes of poor cash flow. A 30-day improvement to change management workflow can generate over $400K in additional cash flow for a $50M contractor.