Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)

The biggest risk for a specialty contractor is the performance of on-site labor.

D. Brown Management Profile Picture
Share

One of the biggest impacts to labor productivity is having a schedule that requires large variations in labor. The most ideal situation is to have a steady ramp up, stable crew size during peak production followed by a steady demobilization.

Field Productivity: Impacts - Unleveled Manpower Schedule.

 

No project will be perfect and impacts to highly variable labor requirements include:

  • Overloading the project to meet demands resulting in too many people during downtimes, which then lowers productivity.  
  • Learning curve for new team members coming on and off the project. Studies show that productivity can be impacted by as much as 10% during the first week for a craftsperson learning a new project. 
  • Overtime required to meet the schedule. Not only will you have the increased cost per hour, but you will experience a decrease in productivity and safety. Four weeks at 5-10’s will impact productivity by 20%.
  • Poor scheduling often goes hand-in-hand with stacking of trades which can cost another 10-50% decrease in productivity for those areas.  
  • There is an increase in the coordination time it takes to move manpower on and off the project which has a direct cost as well as an indirect cost from dilution of management.  

 

 

 


Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

5-Step Foreman Coaching Outline
Accelerating the development of foremen is one of the most critical things a contractor can do to improve project outcomes and mitigate the craft labor shortage. This 5-step outline will form the foundation of a great coaching program.
Changes and Cash Flow Improvement
Construction is a cash-intensive business and change orders are often one of the root causes of poor cash flow. A 30-day improvement to change management workflow can generate over $400K in additional cash flow for a $50M contractor.
Impacted Productivity - Stacking of Trades and Installation Efficiency
Each craftsperson needs about 200 usable square feet for a productive installation. This assumption is included in production units used to estimate and budget projects. Having less than that can impact productivity up to 50%.