Higher Scores Aren’t Always Better: Percent Planned Complete (PPC) Example

Construction is full of competitive personalities - more is always better. This is not always the case, and you must be careful when setting targets that your goals don't have unintended consequences. Percent Planned Complete (PPC) is a perfect example.

Joseph Irby Profile Picture
Share

 

 

Percent Planned Complete (PPC) is a critical measure of a weekly work plan or SIP (Short-Interval Plan). 

David MacNeel from On Point Lean describes that higher scores aren't always better in this interview with Felipe Engineer-Manriquez on the EBFC (Easier, Better, for Construction) Show (4 minutes starting at 0:20:00)

 

 

54% was the average amount of weekly tasks that got completed as planned when Greg Howell and Glenn Ballard first studied the problem in the late 90s. 

Low to Mid 70s: Likely on-track with schedule and productivity (Two Key Results for Project Planning)

High 70s to High 80s: Likely ahead of schedule and productivity targets. 

High 80s to Low 90s: Great team and conditions.

Mid to High 90s: Likely gaming the system - sandbagging or misreporting. 


 

An important part of your scorekeeping process is setting appropriate targets with tolerances and clear management escalations if there are large variances, or they are trending in the wrong direction for too long. 

 



Related Training

Weekly Percent Planned Complete (PPC) and Project Performance
Improving the project planning and delivery process starts with improving predictability around the schedule. Nearly every Superintendent and Foreman is familiar with the Short-Interval-Plan (SIP) and typically fill one out weekly looking ahead 1+ weeks.
Muhammad Ali - Pebble in the Shoe
Construction contracting is largely a game of operational excellence. Between the massive changes going on in the industry and daily operations it is easy for leaders and their teams to overlook the small opportunities for improvement every day.
Last Planner System (LPS) Overview: Should > Can > Will > Did > Improve
The Last Planner System (LPS) developed by the Lean Construction Institute (LCI) is the codification of the practices used by the best project teams. There are elements that EVERY contractor can use to improve performance of their projects and business.