Two Key Results for Project Planning

There are two critical key results that should be focused on as part of every project planning process.

D. Brown Management Profile Picture
Share
  • SCHEDULE:  Completing tasks, milestones and projects WHEN planned.  
  • PRODUCTION:  Completing tasks, milestones and projects for the COST planned.  
Field Productivity: Plan Execution with two key results. By when and how much. Schedule and Production.

These are interrelated but are different.  You can achieve schedule milestones by throwing resources at the problem but that is not sustainable if production budgets are continuously missed.

You will find that by focusing on the scheduling aspect first provides the stability and predictability to continuously improve each week.  This is a large part of the feedback and learning process for project.

The heart of execution at both the schedule and production level starts with defining effective tasks and managing the 6 Pillars of Productivity with rigorous ABC Daily Planning.  

By reviewing schedule feedback weekly that most of the things that impact scheduling are outside of your direct control.  Each week you will learn what really matters most and how to improve your ability to influence the outcomes.   

These two key results assume basics like quality and safety are a non-negotiable part of the culture.


Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Changes in Construction Survey
Changes are a part of the construction process with many underlying causes. While we have all heard the average of 10% changes on construction projects, it is interesting to look at an industry study for validation.
Planning - Integrating the 4 Key Responsibilities
Effective planning combined with regular feedback (at least weekly) combined with a structured look at how to improve each week is the key to integrating the four key responsibilities of a Foreman.
Early Identification as a Trainable Skill
The ability to identify potential changes early is a skill that can be tested, trained, and managed just like a craft skill.