Planning - Integrating the 4 Key Responsibilities

There are four major responsibilities the foreman has that often seem to be competing with each other.

D. Brown Management Profile Picture
Share

Effective planning combined with regular feedback (at least weekly) combined with a structured look at how to improve each week is the key to integrating these four key responsibilities of a Foreman

Field Productivity: Planning, Integrating the four key responsibilites. Safety, Production, Customer Satisfaction, and Quality.

Greg Howell and Glen Ballard founded the Lean Construction Institute (LCI) based on analysis of construction projects showing that on average only 54% of the tasks planned for a week by the Foreman actually got completed. 

They developed The Last Planner System (LPS) that focuses on helping the Foreman plan then execute more effectively.  

The system includes a structured weekly learning element for the project team where they look back at what they accomplished measuring their Percent Plan Complete (PPC) and doing some rapid Root Cause Analysis to improve the process for the following week.  

PPC is a simple measurement - the quantity of tasks that were completed during the week compared to those that were planned.  This is described well in this whitepaper from LCI.

These tools are best used for a whole project team but can be effectively used by a single contractor on a project.  


Planning - Integrating the 4 Key Responsibilities
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Planning - Integrating the 4 Key Responsibilities
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Change Orders and Average Cost Impact to the Project (Industry Survey)
Changes are a part of the construction process with many underlying causes. While we have all heard the average of 10% changes on construction projects, it is interesting to look at an industry study for validation.
Time-on-Tools and Minimum Required Installation
Labor productivity IS NOT the biggest problem with field productivity. Under similar conditions the variation in how fast two crafts people actually “turn wrenches” is about 2X but there are far bigger problems to tackle. Focus on these three areas.
Change Management Fact #1 - It Will Happen
Projects are complex with evolving requirements and changing site conditions. Mistakes will be made. It is how the collective project team manages these changes that ultimately determines success at all levels.