Changes - Impacts Beyond the Direct Costs

Contractors don't typically see the full negative impact of changes and, therefore, don’t put the right level of resources into their management.

D. Brown Management Profile Picture
Share

Typically overlooked impacts that must be quantified include:

Change Management: Impacts Beyond the Direct Costs.
  • Dilution of management on the project, which causes overall loss of productivity.

  • Cash flow that incurs financing costs, as well as potentially keeping a contractor from taking early-pay discounts unless they are very well capitalized.
      
  • Risk of not getting paid for completed change orders is typical and a significant cause of margin fade late in the project.
      
  • Lowered customer satisfaction impacting future work can be the biggest cost of all. However, this does not mean avoiding real changes to the project. 

  • Productivity on the project suffers from many factors related to excessive changes, including dilution of management, schedule compression, overtime, additional mobilizations to the work area, and lower crew morale. 
     
  • Extended project overhead - general conditions.

Contractors, project owners, and architects that fully understand these put the resources in at the earliest design stages driven by weekly meetings and continue managing the project with the same discipline.  



Related Training
More from D. Brown Management
Learning, Doing and Teaching
Growth in life, career, and business is about a continual cycle of learning, doing, and teaching.
Ownership Transition - Key Buyer Risks
While different, buyers of a construction business have just as many risks as sellers. Deeply understanding the risks for both parties is a great start to creating the foundation of a deal.
Delivering Advanced Preconstruction Services
Delivering Advanced Preconstruction Services is the rigorous process of ensuring budgets are met along with maintaining features critical to the project owner / users.