Site Logistics Manager

About 20% of the field labor hours are spent on material logistics and daily mobilization, demobilization to the work area.

D. Brown Management Profile Picture

What if you could shift 5% of the time spent on logistics to installation while accelerating your foreman development?

Field Productivity: Role as a Site Logistics Manager. Mission: Maximize Time-on-Tools (ToT) for Field Crew. 4 Key Results.

Depending on the work study only 50-64% of the work hours are spent on actual installation or “Time-on-Tools”.  

For a $50M per year specialty contractor with labor being about 35% of their job costs this is a savings of OVER $1,000,000 per year.  

Consider changing the role of “Material Handler” being an entry-level person to a role of “Site Logistics Manager.” 

Fill this role with a high-potential crafts person who has already demonstrated capabilities as a lead person overseeing a few people.  This is a role they will fill before being given their own job to run.  

They have 100% accountability for 3 of the 6 pillars of productivity:

They serve as the “Right Hand” and “Second-in-Command” to the Foreman, General Foreman or Project Superintendent who focus on the other 3 pillars of productivity:

  • Right labor scheduled to the right areas of the jobsite.
  • Given the right information for an effective install.
  • Clear production goals set and managed.

The military assigns Generals to run logistics.  Why do contractors typically assign entry level people for something that eats up 20% of the labor?  


Learn more


More from D. Brown Management
Leadership and Management of Details
Building a great contracting business requires the right balance of leadership and management. While it is possible to separate them the truth is that many of the top leaders are relentlessly disciplined managers.
The Leadership Vibrancy Curve
Leaders must navigate (1) the stages of contractor growth, (2) the phases of management team development, and (3) the arc of their own career and life. Maintaining the right levels of leadership vibrancy leads to sustainable scaling and succession.
Thriving with a Difficult Manager
In the ideal situation, everyone would have a great manager - both internally and externally. In the real world, we will all have to work for someone we consider a difficult manager. Learn to thrive in these situations.