Percent Planned Complete (PPC) - Calculation Example

Yoda would be the perfect coach for managing schedules on projects:

D. Brown Management Profile Picture
Share

“Do or do not. There is no try.”

Yoda
Field Productivity: Percent Planned Complete (PPC). Do or do not. There is no try.

This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement.  Measurement of PPC is rigorous:

  • Partially complete tasks DO NOT matter.
  • Extra tasks (not planned) DO NOT count.
  • Reasons why DO NOT matter except for the weekly learning aspect. 

Imagine designing a field supervisor coaching program with PPC at the center.  

For 12 weeks an experienced coach would work hands-on with a Foreman starting with a review of their PPC from the prior week then developing the next week’s Short-Interval-Plan (SIP) focusing on:  

This coaching will improve the Foreman’s capability to execute their key responsibilities and achieve their key results.  


Field Productivity Workshop


Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Succession Process and Architectural Design Phases
As contractors prepare for succession, they should use the same lessons they have learned in developing and then building projects.
Talent: 9 Processes to Master
Contractors who master talent will be the winners tomorrow as the shortage of critical talent will continue to impact all industries.
Incentive Compensation for Contractors - Audience Question: Keep Why Top Of Mind?
Incentive programs can be as seemingly small and informal as a handshake from a manager for a job well done up to very large cash compensation.