Percent Planned Complete (PPC) - Calculation Example

Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.”

D. Brown Management Profile Picture
Share
Field Productivity: Percent Planned Complete (PPC). Do or do not. There is no try.

This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement. Measurement of PPC is rigorous:

  • Partially complete tasks DO NOT count.
  • Extra tasks (not planned) DO NOT count.
  • Reasons why DO NOT matter except for the weekly learning aspect. 

Imagine designing a field supervisor coaching program with PPC at the center.  

For 12 weeks, an experienced coach would work hands-on with a Foreman starting with a review of their PPC from the prior week and then developing the next week’s Short-Interval-Plan (SIP), focusing on:  

This coaching will improve the Foreman’s capability to execute their key responsibilities and achieve their key results.  


Field Productivity Workshop



Related Training
More from D. Brown Management
Leadership and Management of Details
Building a great contracting business requires the right balance of leadership and management. While it is possible to separate them the truth is that many of the top leaders are relentlessly disciplined managers.
The Leadership Vibrancy Curve
Leaders must navigate (1) the stages of contractor growth, (2) the phases of management team development, and (3) the arc of their own career and life. Maintaining the right levels of leadership vibrancy leads to sustainable scaling and succession.
Thriving with a Difficult Manager
In the ideal situation, everyone would have a great manager - both internally and externally. In the real world, we will all have to work for someone we consider a difficult manager. Learn to thrive in these situations.